What is it?
Brown Paper Planning is a technique that uses a large area of brown paper to map a process.
It creates a visual representation of activities, interfaces, decision points, and information sources.
Why is it useful?
- Engages the team in planning together, building ownership of the work.
- Focuses on the process of developing the plan rather than just the output (e.g. a gantt chart).
- Captures roles, timelines, and activities in swim lanes.
- Highlights milestones, interfaces, decision points, and deliverables.
Downloads
- Download for Microsoft PowerPoint
- Download for Apple Keynote
- Download in PDF
Objective
To engage the team in planning all the tasks, roles, and timelines required to implement a project or change initiative.
When would you use it?
- When it is time to plan how a change or project will be delivered.
- When you want to increase buy-in and build ownership from key stakeholders.
Resources Required
- 1 hour
- Large sheet of brown or blank paper (approx. 2m x 4m) fixed to a wall
- Post-it notes (different colours for different workstreams)
- Flip-chart marker pens
- Space for participants to stand and move around
Process
1. Prepare the paper
- Mark out the paper with workstreams, swim lanes, and a timeline.
2. Identify workstreams
- Decide how to divide the work (e.g. by stakeholder, function, or role).
- Each workstream becomes a row (swim lane) on the paper.
3. Add the timeline
- Draw a timeline across the top, working backwards from the end date to the start date.
- Divide it into blocks that make sense (weeks, months, terms).
4. Plot milestones
- Identify key milestones (deliverables, events, decision points).
- Write each milestone on a square Post-it, placed as a diamond shape.
5. Add activities
- Use coloured Post-its to represent activities in each swim lane.
- Stretch them across the timeline to show duration.
- Label clearly with the activity name.
6. Map dependencies
- Draw lines between activities where one depends on another.
7. Compare across swim lanes
- Have each team member or subgroup plan their own swim lane.
- Bring all streams together to challenge, refine, and align thinking.
Secret Sauce
- Never plan alone – give each swim lane to a different person or subgroup.
- Always start with milestones, working backwards from the final deliverable.
- Use colour coding to make workstreams clear at a glance.
- Encourage cross-challenge between workstreams to surface dependencies and risks early.